If a Project Involves Risk, Managers Can Account for the Risk

Question 104

Multiple Choice

If a project involves risk, managers can account for the risk by_______ the discount rate, which _______the present value of the future profits.


A) decreasing; increases
B) increasing; decreases
C) increasing; increases
D) decreasing; decreases