Multiple Choice
The most commonly used method of connecting tilt- up walls to the slab- on- ground is
A) a continuous steel angle welded to panels and the slab- on- ground.
B) a continuous concrete closure strip in the slab- on- ground.
C) individual steel plates welded to panels and the slab- on- ground.
D) A or C.
E) B or C.
Correct Answer:

Verified
Correct Answer:
Verified
Q39: In a tilt- up wall building, the
Q40: Compared to a longitudinal- bearing wall floor
Q41: The clear height of openings in CMU
Q42: Why do multistory, load- bearing wall buildings
Q43: What is the role of vertical reinforcement
Q45: What are the bond beams in masonry
Q46: To provide continuous insulation in a tilt-
Q47: With the help of a sketch, explain
Q48: With the help of sketches and notes,
Q49: A load- bearing wall structure works best