Multiple Choice
The finishing operations of a concrete surface usually involve striking, floating, and troweling. The sequence in which these three operations are generally performed is
A) striking, troweling, and floating.
B) troweling, floating, and striking.
C) striking, floating, and troweling.
D) floating, striking, and troweling.
Correct Answer:

Verified
Correct Answer:
Verified
Q68: Why is the setting and hardening of
Q69: Which type of Portland cement is commonly
Q70: List various types of Portland cement and
Q71: Explain the difference between air entrainment and
Q72: The minimum water- cement ratio for complete
Q74: Describe how lime- sand mortar hardens and
Q75: What is a water- reducing agent (WRA)and
Q76: In a high- rise building, the concrete
Q77: Quicklime is most commonly used in building
Q78: Define: (i)concrete and (ii)concrete admixture.