Multiple Choice
The surety bonds used in a typical construction contract are
A) bid bond, performance bond, and payment bond.
B) bid bond, contract award bond, and completion bond.
C) bid bond, performance bond, and completion bond.
D) prescreening bond, award bond, and completion bond.
E) none of the above.
Correct Answer:

Verified
Correct Answer:
Verified
Q20: Of the four project delivery methods, which
Q21: The final completion inspection of the project
Q22: What are shop drawings, why are they
Q23: In which of the three documents (construction
Q24: In reality, who bears the cost of
Q26: Explain the difference between change orders and
Q27: The specifications of a typical building project
Q28: The construction drawings for a building project
Q29: All required surety bonds must be provided
Q30: Sketch in three dimensions the hypothetical building