Multiple Choice
You are given a job to make a decision on project X, which is composed of three independent projects A, B, and C that have NPVs of + $70, -$40 and + $100, respectively. How would you go about making the decision about whether to accept or reject the project?
A) Accept project X as it has a positive NPV.
B) Reject project X.
C) Break up the project into its components: Accept A and C, but reject B.
D) Break up the project into its components: Accept C.
Correct Answer:

Verified
Correct Answer:
Verified
Q48: If the NPV of project A is
Q49: In the case of a loan project
Q50: The following are measures used by firms
Q51: The cost of a new machine is
Q52: Dry-Sand Company is considering investing in a
Q54: Accounting earnings from a firm's income statement,
Q55: Discuss some of the disadvantages of the
Q56: If the cash flows for Project M
Q57: There can never be more than one
Q58: The following table gives the available projects