Gerald was a subcontractor,bidding on a contract for XYZ Corp.,the general contractor.When adding up the total of materials and labor,Gerald's secretary made a clerical error with a total of $45,000 instead of $450,000.Gerald then submitted his bid for $45,000.XYZ accepted Gerald's bid of $45,000,mostly because all the other bids were over $400,000.When Gerald learns of his mistake,he tells XYZ that he cannot perform the contract.If XYZ sues to enforce this contract,what is the most likely result?


A) The contract is fully enforceable because there was a valid offer and acceptance.
B) This is a bilateral mistake,so either party can rescind the contract.
C) This is a unilateral mistake,which can usually be rescinded by the mistaking party.
D) Because XYZ should have known that this was an error,Gerald will be allowed to rescind the contract.
E) This is a case of economic duress and Gerald will be allowed to rescind the contract.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions