Multiple Choice
The general requirements for a liquidated damages clause to be enforceable are which of the following?
A) Actual damages are difficult to determine and the liquidated damages amount is reasonable.
B) Actual damages exceed the amount foreseen by the parties.
C) The liquidated damages clause applies only to unforeseeable damages.
D) The breaching party used its best efforts to avoid a breach of the contract.
E) The parties have rescinded the contract.
Correct Answer:

Verified
Correct Answer:
Verified
Q55: Lost profits can be recovered as consequential
Q56: When there is an anticipatory breach,the nonbreaching
Q57: When a client breaches a contract with
Q59: What kinds of damages will be awarded
Q61: The UCC governs damages for a breach
Q62: Only those consequential damages that are unforeseeable
Q64: Which of the following is true about
Q65: Justin purchased a new Ford Thunderbird in
Q70: Intentional interference with contractual relations requires a
Q112: Liquidated damages clauses will generally not be