Multiple Choice
A construction contractor entered into a contract to build a family room addition onto Harry's home for $25,000.In order to encourage timely performance,the agreement provided that the contractor would be penalized $2,000 as liquidated damages for each day that the project was late in getting finished.The contractor was 30 days late in finishing the project,but otherwise met the terms of the agreement.What is most likely in this situation?
A) The liquidated damages clause would not be enforced due to its being excessive.
B) The liquidated damages clause would be limited to $25,000,the amount of the contract price.
C) The liquidated damages clause would be enforced.
D) The liquidated damages clause would not be enforced because the parties made a mutual mistake about when the contract would be finished.
Correct Answer:

Verified
Correct Answer:
Verified
Q16: Which of the following is not a
Q18: When a court orders specific performance,it:<br>A) orders
Q19: Betty is retired and works on antique
Q22: If Julia agrees to construct a platinum
Q23: Which of the following types of damages
Q24: Henry took his Porsche to the shop
Q26: If an employee breaches an employment contract,the
Q47: The general standard to obtain an injunction
Q132: A contractor is generally entitled to recover
Q141: Why is the general measure of compensatory