________ Is a Network of Project Activities Showing Both the Estimates

Question 75

Multiple Choice

________ is a network of project activities showing both the estimates of time necessary to complete each activity and the sequence of activities that must be followed to complete the project.


A) Gantt bar graph evaluation technique
B) Target skill objective
C) Product lifecycle technique
D) Program evaluation and review technique
E) Organizational evaluation technique