Which one of the following is NOT a step in designing a PERT network?
A) determining how much time is needed to complete activities and events
B) identifying the critical path
C) identifying financial resources needed to complete activities
D) listing all activities and events that must be accomplished for the project
E) designing a PERT network that reflects activities,events,and time needed