Multiple Choice
The critical path in a PERT chart represents the _____.
A) sequence of operations that involves outside suppliers
B) sequence of operations that requires the longest time for completion
C) areas of operations that require the least amount of technical support
D) areas of operations that have abundant and extra time
Correct Answer:

Verified
Correct Answer:
Verified