    Ehshan Sets the Deadlines for an Upcoming Project
Solved

Ehshan Sets the Deadlines for an Upcoming Project

Question 86

Question 86

Multiple Choice

Ehshan sets the deadlines for an upcoming project.This depicts _____ planning.


A) operational
B) tactical
C) strategic
D) contingency

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q81: FlipTech Inc.is a cell phone service provider

Q82: Bernardo's job is to assess the success

Q83: Most top executives started out as<br>A)technical experts.<br>B)chartered

Q84: The first step in the strategic planning

Q85: In the context of a company's strategic

Q87: _ determines the primary objectives of an

Q88: Remo is a member of his firm's

Q89: A petroleum refinery stockpiles crude oil so

Q90: Decisions involving simple,common,frequently occurring problems for which

Q91: Which of the following has Keller Williams

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines