Multiple Choice

In an assembly line of a factory that makes gears,it takes fifteen minutes to complete a drilling operation using a lathe.The duration of this operation is called _____ time.


A) delay
B) queue
C) processing
D) standard

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q1: Which of the following performance perspectives in

Q4: Which of the following is a financial

Q11: In the context of the triple bottom

Q16: In the context of the value chain

Q19: Which of the following performance perspectives in

Q25: The time required to ramp up to

Q26: _ measures include environmental measures such as

Q28: In the context of the types of

Q30: According to research, which of the following

Q32: Actionable measures are not bound by time.

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines