Multiple Choice
What are specific factors that can limit options including budget, delivery dates, available skilled resources, and organizational policies?
A) Project objectives
B) Project constraints
C) Project assumptions
D) Project deliverable
Correct Answer:

Verified
Correct Answer:
Verified