Multiple Choice
What is an activity-based process in which each phase in the SDLC is performed sequentially from planning through implementation and maintenance?
A) RAD methodology
B) Agile methodology
C) Waterfall methodology
D) Extreme programming
Correct Answer:

Verified
Correct Answer:
Verified