Multiple Choice
Which phase brings all the project pieces together into a special testing environment to eliminate errors and bugs and verify that the system meets all the business requirements defined in the analysis phase?
A) Testing phase
B) Analysis phase
C) Development phase
D) Planning phase
Correct Answer:

Verified
Correct Answer: