Multiple Choice
Which of the following is a scheduling tool that breaks down large projects into steps to be performed and specifies the time required to perform each one?
A) Myers graphic
B) critical path chart
C) Gantt chart
D) process analysis graph
E) master schedule
Correct Answer: