Multiple Choice
Logan Aluminum makes coils of aluminum that it supplies to customer companies that use it to make beverage cans.Logan uses a schedule that specifies how many tons of each type of coil will be produced each week.What is this schedule called?
A) master production schedule
B) detailed schedule
C) Gantt chart
D) staff schedule
E) PERT chart
Correct Answer:

Verified
Correct Answer: