A flood will require mining operations to cease for at least six months.How would a force majeure clause affect the legal status of the miner's obligations relating to its existing supply contracts?
A) non-performance of the contract will be excused without liability
B) the innocent party will have the right to terminate and sue for breach
C) performance obligations will be suspended until a specified event occurs
D) the innocent party will have the right to sue for damages for breach
Correct Answer:

Verified
Correct Answer:
Verified
Q33: Within each provincial jurisdiction,a beneficiary under an
Q34: Novation of a contract will result in
Q35: Everyone who suffers a breach of contract
Q36: Randall was wrongfully dismissed from his job
Q37: An assignee is entitled to collect the
Q39: The courts are reluctant to allow a
Q40: An assignee's rights can be no greater
Q41: Donelle agreed to rent her cottage to
Q42: Recovery for non-pecuniary damages is not possible
Q43: Albert entered into a contract under the