A flood will require mining operations to cease for at least six months.How would a force majeure clause affect the legal status of the miner's obligations relating to its existing supply contracts?


A) non-performance of the contract will be excused without liability
B) the innocent party will have the right to terminate and sue for breach
C) performance obligations will be suspended until a specified event occurs
D) the innocent party will have the right to sue for damages for breach