Compute the PI Statistic for Project X and Note Whether

Question 120

Multiple Choice

Compute the PI statistic for Project X and note whether the firm should accept or reject the project with the cash flows shown as follows if the appropriate cost of capital is 10 percent.
Time: 012345Cash flow:757501007550\begin{array}{l}\begin{array} {| l | l | l | l | l | l | l |}\hline\text {Time: }&0&1&2&3&4&5\\\hline\text {Cash flow:}&-75&-75&0&100&75&50\\\hline\end{array}\end{array}


A) 10 percent, reject
B) 14.22 percent, accept
C) 13.26 percent, accept
D) 18.96 percent, accept