Carbon Corporation Had a $2,000,000 Contract to Build a Small

Question 64

Multiple Choice

Carbon Corporation had a $2,000,000 contract to build a small hospital with total costs estimated at $1,600,000.It received the following payments and incurred the following expenses over the three-year contract period:Carbon Corporation had a $2,000,000 contract to build a small hospital with total costs estimated at $1,600,000.It received the following payments and incurred the following expenses over the three-year contract period:  Under the competed contract method of accounting, how much profit (loss)  should Carbon recognize in years 1, 2, and 3 respectively? A) $0, $0, $250,000 B) $0, $0, $400,000 C) $100,000, $300,000, ($150,000)  D) $75,000, $225,000, ($50,000)
Under the competed contract method of accounting, how much profit (loss) should Carbon recognize in years 1, 2, and 3 respectively?


A) $0, $0, $250,000
B) $0, $0, $400,000
C) $100,000, $300,000, ($150,000)
D) $75,000, $225,000, ($50,000)

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions