Multiple Choice
In relation to the drum-buffer-rope concept that is used to maximise flow through an organisational bottleneck, the statement that is correct is:
A) the 'buffer' is the activity of only maintaining a small amount of work in process
B) the 'rope' involves calculating the demand for materials according to specified lead times
C) the 'drum' relates to the activity associated with only inserting materials into the constraint when needed
D) All the statements are correct
Correct Answer:

Verified
Correct Answer:
Verified
Q22: Which of these is not a benefit
Q23: The statement concerning the theory of constraints
Q24: Advantages of just-in time inventory management are
Q25: Lean accounting refocuses performance measurement systems to
Q26: The originator of the total quality management
Q28: The first stage in the lean accounting
Q29: Which of the following terms is typically
Q30: A just-in-time system reduces costs in all
Q31: 'Value' in lean accounting is defined through
Q32: A limitation of the theory of constraints