Multiple Choice
A company is considering a project with a cash break-even point of 14,500 units. The selling price is $14 a unit and the variable cost per unit is $8. What is the projected amount of fixed costs?
A) $87,000
B) $94,000
C) $109,000
D) $116,000
E) $203,000
Correct Answer:

Verified
Correct Answer:
Verified