To ascertain whether the accuracy of the variable cost estimate for a project will have much effect on the final outcome of the project, you should probably conduct _____ analysis.


A) Leverage.
B) Scenario.
C) Break-even.
D) Sensitivity.
E) Cash flow.

Correct Answer: