Multiple Choice
Conventional capital budgeting analysis will tend to understate the true NPV of a project if any of the following are present EXCEPT:
A) Contingency plan options.
B) The option to default.
C) The option to expand.
D) The option to abandon.
E) The option to wait.
Correct Answer:

Verified
Correct Answer:
Verified