The following tasks were identified for a major project using a WBS. Optimistic, most likely, and pessimistic task completion times for each task were also identified. Compute task times, task variances, project variance, and project standard deviation for this project.
The following tasks were identified for a major project using a WBS. Optimistic, most likely, and pessimistic task completion times for each task were also identified. Compute task times, task variances, project variance, and project standard deviation for this project.

Correct Answer:

verifed

Verified

Expected time = (a + 4m + b)/6...