Multiple Choice
When building a house or constructing an airplane that must be completed by a certain date, which type of scheduling should be used?
A) forward scheduling
B) backward scheduling
C) horizontal scheduling
D) vertical scheduling
Correct Answer:

Verified
Correct Answer:
Verified