menu-iconExamlexExamLexServices

Discover

Ask a Question
  1. All Topics
  2. Topic
    Business
  3. Study Set
    Managing Supply Chain Study Set 1
  4. Exam
    Exam 12: Project Management
  5. Question
    In a Project Network,the Critical Path Is the Sequence of Activities
Solved

In a Project Network,the Critical Path Is the Sequence of Activities

Question 6

Question 6

Multiple Choice

In a project network,the critical path is the sequence of activities which has the


A) most tasks.
B) most nodes.
C) most events.
D) longest time.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q1: The act of celebrating successes,releasing resources,including people,and

Q2: The act of leading and directing the

Q3: The shortest time for completing a project

Q4: The act of applying more resources to

Q5: The phase of the project in which

Q7: The path in a network with the

Q8: The network diagram describes sequential relationships among

Q9: Following are the three time estimates for

Q10: The scope or participation in a Tiger

Q11: A tool for monitoring who is assigned

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines