True/False
The earliest finish time for a task is equal to the latest finish time minus the task time.
Correct Answer:

Verified
Correct Answer:
Verified
Related Questions
Q67: The project team stage of development when
Q68: The best estimate for the time required
Q69: Allowing the deliverables of a project to
Q70: The project planning step of estimating activity
Q71: As per Hersey and Blanchard's Situation Leadership
Q73: Task C is directly preceded by two
Q74: The project charter is most likely to
Q75: Specialists that are assigned full-time to a
Q76: The longest foreseeable task completion time is
Q77: The formula which helps compute project times