Question 72

Question 72

True/False

The earliest finish time for a task is equal to the latest finish time minus the task time.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q67: The project team stage of development when

Q68: The best estimate for the time required

Q69: Allowing the deliverables of a project to

Q70: The project planning step of estimating activity

Q71: As per Hersey and Blanchard's Situation Leadership

Q73: Task C is directly preceded by two

Q74: The project charter is most likely to

Q75: Specialists that are assigned full-time to a

Q76: The longest foreseeable task completion time is

Q77: The formula which helps compute project times

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines