menu-iconExamlexExamLexServices

Discover

Ask a Question
  1. All Topics
  2. Topic
    Business
  3. Study Set
    Managing Supply Chain Study Set 1
  4. Exam
    Exam 12: Project Management
  5. Question
    The Standard Deviation of the Critical Path Is Equal to the Sum
Solved

The Standard Deviation of the Critical Path Is Equal to the Sum

Question 61

Question 61

True/False

The standard deviation of the critical path is equal to the sum of the standard deviations of all of the tasks on the critical path.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q56: A sequence of activities that leads from

Q57: The shortest time for completing a project

Q58: The act of determining which tasks precede

Q59: The latest starting time for a task

Q60: As per Belbin,a person who has the

Q62: Key phases in a project time line

Q63: Developing the preliminary project scope statement is

Q64: Tasks not on the critical path have

Q65: Developing the project charter is a key

Q66: Developing the project charter is a key

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines