In the Level SOP Production Plan,variations in Demand from Period

Question 42

Multiple Choice

In the level SOP production plan,variations in demand from period to period are met by


A) varying production levels by adjusting employment levels.
B) varying production levels without adjusting employment levels.
C) changing price levels.
D) using inventory buffers.

Correct Answer: