The Element of the MRP Record Which Is the Quantity

Question 6

Multiple Choice

The element of the MRP record which is the quantity that has already been ordered and will be received at the beginning of the period is called


A) gross requirements.
B) net requirements.
C) scheduled receipts.
D) planned order receipts.

Correct Answer: