Multiple Choice
The element of the MRP record which is the amount of an item required to satisfy gross requirements after taking scheduled receipts and projected inventory in account is called
A) gross requirements.
B) net requirements.
C) scheduled receipts.
D) planned order receipts.
Correct Answer:

Verified
Correct Answer:
Verified