The materials manager for a tire manufacturer must periodically place orders for a key chemical,one of the raw materials used in producing tires.The manager knows that manufacturing uses the chemical at a rate of 300 lbs.each week,and the lead time for delivery is 4 days.Assume that the manufacturing operation runs 5 days a week.At what point should the chemical be reordered?


A) When 0 lbs.are remaining
B) When 240 lbs.are remaining
C) When 375 lbs.are remaining
D) When 1200 lbs.are remaining