Multiple Choice
Use the information below to answer the following question(s) .
A computer manufacturer procures memory chips from its key supplier.The tool that the manufacturer uses to monitor the part supplier is a supplier scorecard.With respect to delivery performance,the primary performance metric monitored is the percentage of orders delivered complete and on-time.The manufacturer also monitors the supplier's service performance and measures the invoice accuracy rate (% of invoices that are accurate) .The following measures are used for the scoring criteria:
Data collected on the supplied orders over the present quarter indicated that 350 orders were delivered and out of these 10 orders were incomplete,5 orders were late and another 15 orders were incomplete and late.Also out the 350 invoices for the shipments delivered,there were errors on 50 invoices.
-What is the delivery performance-i.e. ,percentage of order delivered complete and on-time for this quarter?
A) 95%
B) 91.5%
C) 83.2%
D) 75%
Correct Answer:

Verified
Correct Answer:
Verified
Q6: The first step in the supplier management
Q7: Which of the following suppliers is not
Q8: A supplier scorecard is used for price
Q9: Many firms are focused on helping their
Q10: The kind of supplier relationship that is
Q12: Use the information below to answer the
Q13: The first step in the supplier development
Q14: The process of helping a supplier improve
Q15: A specification for services is known as
Q16: The Apple Supplier Code of Conduct outlines