Multiple Choice
Which of the following is the critical step in scheduling because a holdup in one department could cause a shutdown in the rest of the plant?
A) Routing
B) Sequencing
C) Dispatching
D) Controlling
Correct Answer:

Verified
Correct Answer:
Verified