Multiple Choice
TJ is coordinating a project.Which would he probably NOT use to avoid conflicts?
A) Encourage a competitive edge between team members
B) Clearly defining plans for the project
C) Develop a project charter
D) Look at other projects and priorities and see how that might impact the project
E) Communicate the business value to the team
Correct Answer:

Verified
Correct Answer:
Verified