Multiple Choice
Micah is a fairly new project manager.He estimated for a project plan (on the planning phase) that the project would cost $50,000 and take 20 weeks.According to the margin of error guidelines for well-done estimates,that could range from:
A) $0 and $100,000 - and between 15 and 25 weeks
B) $10,000 and $60,000 - and between 12 and 28 weeks
C) $0 and $100,000 - and between 0 and 40 weeks
D) $5,000 and $100,000 - and between 10 and 30 weeks
E) $25,000 and $75,000 - and between 10 and 30 weeks
Correct Answer:

Verified
Correct Answer:
Verified
Q31: A critical success factor in project management
Q32: Kumar is the project manager for a
Q33: Which of the following methodologies might be
Q34: Which is a true statement about IT
Q35: Extreme programming requires a great deal of
Q37: The margin of error in cost and
Q38: PMP is People - Management - Project
Q39: Which of the following methodologies might be
Q40: The Waterfall Methodology breaks the overall project
Q41: Which of the following methodologies might be