Micah Is a Fairly New Project Manager

Question 36

Multiple Choice

Micah is a fairly new project manager.He estimated for a project plan (on the planning phase) that the project would cost $50,000 and take 20 weeks.According to the margin of error guidelines for well-done estimates,that could range from:


A) $0 and $100,000 - and between 15 and 25 weeks
B) $10,000 and $60,000 - and between 12 and 28 weeks
C) $0 and $100,000 - and between 0 and 40 weeks
D) $5,000 and $100,000 - and between 10 and 30 weeks
E) $25,000 and $75,000 - and between 10 and 30 weeks

Correct Answer:

verifed

Verified