Multiple Choice
Garrett has been told by management that his project MUST be completed on time.His best estimates are more than two weeks after the absolute deadline.Which technique could he use to get a functional system on time?
A) Risk management
B) System prototyping
C) Benchmarking
D) Timeboxing
E) Activity elimination
Correct Answer:

Verified
Correct Answer:
Verified