If a program module is taking longer to develop than expected,the recommended action is:


A) Put more programmers on the staff
B) Force the developers to work weekends to catch up
C) Move the expected completion date back
D) Incorporate scope creep into the requirements
E) Change the development environment into an object-oriented language