Generally When Assigning Programming Development Tasks,the Project Manager Will Analyze

Question 34

True/False

Generally when assigning programming development tasks,the project manager will analyze skill levels and capabilities of programming staff and also analyze the modules for complexity and try to match complex modules to more experienced and skilled programming developers.