Craft Construction entered into a contract to construct a generator station for a utility customer. The project was started in 2016 and completed in 2017. Cost and other information is presented below.
20162017 Costs incurred during the year $225,000$550,000 Estimated costs to complete 450,0000 -  Billings during the year 200,000700,000 Cash collections during the year 150,000750,000\begin{array}{lrc}&2016&2017\\\text { Costs incurred during the year } & \$ 225,000 & \$ 550,000 \\\text { Estimated costs to complete } & 450,000 & -0 \text { - } \\\text { Billings during the year } & 200,000 & 700,000 \\\text { Cash collections during the year } & 150,000 & 750,000\end{array}

-Refer to Craft Construction. Assume Craft uses the percentage-of-completion method for revenue recognition. Compute the amount of gross profit for 2016 and 2017.

Correct Answer:

verifed

Verified

None...

View Answer

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions