Multiple Choice
A company must perform a maintenance project consisting of seven activities. The activities, their predecessors, and their respective time estimates are presented below: Using CPM, what is the Latest Finish Time for the last activity in this project (i.e., the total time to complete the project) ?
A) 9 days
B) 10 days
C) 11 days
D) 12 days
E) 13 days
Correct Answer:

Verified
Correct Answer:
Verified