Multiple Choice
You have collected the data for a Time-Cost CPM Scheduling model analysis. The time is in days and the project "direct costs" are given below. The indirect costs for the project are determined on a daily duration basis. If the project lasts 16 days the total indirect costs are $400, 15 days they will be $250, 14 days they will be $200, and 13 days they will be $100. If you crash this project by one day what is the total (i.e., direct and indirect) project cost?
A) $2,150
B) $2,300
C) $2,400
D) $2,450
E) $2,500
Correct Answer:

Verified
Correct Answer:
Verified
Q14: The activity direct costs associated with a
Q14: PERT is an abbreviation for which of
Q18: In CPM analysis, it is generally expected
Q19: Which of the following is a graphic
Q21: You are managing a project and need
Q39: When reducing the planned duration of a
Q54: Below are the data for a Time-Cost
Q56: What does "EVM" stand for?<br>A) Extra Value
Q63: One of the advantages of a functional
Q85: Earned value management (EVM) is a technique