Solved

You Have Collected the Data for a Time-Cost CPM Scheduling

Question 51

Multiple Choice

You have collected the data for a Time-Cost CPM Scheduling model analysis. The time is in days and the project "direct costs" are given below. The indirect costs for the project are determined on a daily duration basis. If the project lasts 16 days the total indirect costs are $400, 15 days they will be $250, 14 days they will be $200, and 13 days they will be $100. If you crash this project by one day what is the total (i.e., direct and indirect) project cost?
You have collected the data for a Time-Cost CPM Scheduling model analysis. The time is in days and the project  direct costs  are given below. The indirect costs for the project are determined on a daily duration basis. If the project lasts 16 days the total indirect costs are $400, 15 days they will be $250, 14 days they will be $200, and 13 days they will be $100. If you crash this project by one day what is the total (i.e., direct and indirect)  project cost?   A)  $2,150 B)  $2,300 C)  $2,400 D)  $2,450 E)  $2,500


A) $2,150
B) $2,300
C) $2,400
D) $2,450
E) $2,500

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions