Multiple Choice
You have collected the data for a Time-Cost CPM Scheduling model analysis. The time is in days and the project "direct costs" are given below. The indirect costs for the project are determined on a daily duration basis. If the project lasts 16 days the total indirect costs are $400, 15 days they will be $250, 14 days they will be $200, and 13 days they will be $100. At what day do we achieve the lowest total project cost (i.e., direct plus indirect costs) ?
A) 16 days
B) 15 days
C) 14 days
D) 13 days
E) 12 days
Correct Answer:

Verified
Correct Answer:
Verified
Q26: An event unit package is a subdivision
Q39: Calculating the early start and early finish
Q44: A project may be defined as a
Q54: Below are the data for a Time-Cost
Q56: What does "EVM" stand for?<br>A) Extra Value
Q63: One of the advantages of a functional
Q65: A project starts out as which of
Q85: Earned value management (EVM) is a technique
Q90: The critical path of activities in a
Q104: In CPM, the late start time estimate