You Have Collected the Data for a Time-Cost CPM Scheduling

Question 58

Multiple Choice

You have collected the data for a Time-Cost CPM Scheduling model analysis. The time is in days and the project "direct costs" are given below. The indirect costs for the project are determined on a daily duration basis. If the project lasts 16 days the total indirect costs are $400, 15 days they will be $250, 14 days they will be $200, and 13 days they will be $100. At what day do we achieve the lowest total project cost (i.e., direct plus indirect costs) ?
You have collected the data for a Time-Cost CPM Scheduling model analysis. The time is in days and the project  direct costs  are given below. The indirect costs for the project are determined on a daily duration basis. If the project lasts 16 days the total indirect costs are $400, 15 days they will be $250, 14 days they will be $200, and 13 days they will be $100. At what day do we achieve the lowest total project cost (i.e., direct plus indirect costs) ?   A)  16 days B)  15 days C)  14 days D)  13 days E)  12 days


A) 16 days
B) 15 days
C) 14 days
D) 13 days
E) 12 days

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions