Multiple Choice
The fixed manufacturing overhead variance caused by actual activity being different from the estimated activity used in calculating the predetermined overhead application rate is called the:
A) spending variance.
B) budget variance.
C) efficiency variance.
D) volume variance.
Correct Answer:

Verified
Correct Answer: