The Part of the Variable Overhead Budget Variance Due to the Difference

Question 17

Multiple Choice

The part of the variable overhead budget variance due to the difference between actual variable overhead cost and the standard cost allowed for the actual inputs used is called the:


A) variable overhead spending variance.
B) variable overhead budget variance.
C) variable overhead efficiency variance.
D) variable overhead volume variance.