Multiple Choice
The part of the variable overhead budget variance due to the difference between actual variable overhead cost and the standard cost allowed for the actual inputs used is called the:
A) variable overhead spending variance.
B) variable overhead budget variance.
C) variable overhead efficiency variance.
D) variable overhead volume variance.
Correct Answer:

Verified
Correct Answer:
Verified
Q12: The principal objective of a performance report
Q13: The decision rule to determine what budget
Q14: The standards for one case of
Q15: AAA Export Company's actual production for March
Q16: How are unfavorable standard cost variances reported
Q18: Which of the following is true about
Q19: Which of the following product cost components
Q20: The difference between standard and actual cost
Q21: A technique for filtering cost information within
Q22: How is performance evaluated for a profit