Multiple Choice
Kimberley, a project manager in a software development company, is assigned a new project. She is given a budget of $500,000 and a span of six months to complete the project. In three months, she is able to complete 50 percent of the project. In this scenario, the earned value of the work completed is _____.
A) $350,000
B) $300,000
C) $250,000
D) $200,000
E) $150,000
Correct Answer:

Verified
Correct Answer:
Verified