Multiple Choice
Alice, a project manager, has undertaken a project to build an irrigation canal. Based on the resources allocated to her, she makes an initial estimate that the time required to dig the canal would be 20 days. She also prepares an alternative estimate by adding an additional resource that will allow the project to be completed in 10 days. This alternative estimate that Alice prepares is referred to as the _____.
A) crash duration
B) standard duration
C) slope duration
D) buffer duration
E) critical duration
Correct Answer:

Verified
Correct Answer:
Verified
Q47: What is resource leveling? Why is it
Q48: Explain how you would choose a priority
Q49: What is the student syndrome? In what
Q50: Schedule slippage simply measures the amount by
Q51: Which of the following priority rules makes
Q53: The following describes which priority rule: asks
Q54: Fast-tracking a project is used primarily in
Q55: According to research, the best overall priority
Q56: All tasks can be crashed to some
Q57: Often it is beneficial to crash activities