In the Design Structure Matrix
A) the rows correspond to tasks and the columns correspond to resources
B) both the rows and columns correspond to tasks
C) the rows correspond to tasks and the columns correspond to functional departments
D) the rows correspond to resources and the columns correspond to tasks
E) the rows correspond to resources and the columns correspond to functional departments
Correct Answer:

Verified
Correct Answer:
Verified